Timeline

Luchtfoto 2025

Luchtfoto 2025
jan 2025

Monitoring CAWM components in progress

FEB-MAY 2024

Re-Start monitoring effluent helophyte filter and digester

FEB-MAY 2024

Luchtfoto 2024

jan 2024

Start monitoring rainwater treatment system

DEC 2023

Monitoring completed

JULY 2023

infiltration area incl wadi constructed

MAY 2023

rainwater gathering constructions completed (concrete pavement & gabions)

MAY 2023

Luchtfoto 2023

jan 2023

Adjustments rainwater treatment plant/ testing phase completed

OCT 2022

inline monitoring testing phase completed

SEPT 2022

Digester constructed and tested

APRIL 2022

inline monitoring/ rainwater piping connected to storage buffer

MARCH 2022

First inhabitants apartment building

FEB 2022

Inline monitoring equipment flooded, construction infrastructure in progress

JAN 2022

Luchtfoto 2022

jan 2022

Apartment building constructed

DEC 2021

Apartment building Indoor water saving installations/ food waste grinder installed

DEC 2021

Helophyte filter installed and tested

AUG 2021

rainwater treatment plant constructed & energy- and operating system installed

Q2-Q3 2021

Housing units rainwater treatment plant installed

MARCH 2021

15 Houses First inhabitants

JAN 2021

Luchtfoto 2021

jan 2021

15 houses Indoor water saving installations/ food waste grinders installed

DEC 2020

15 Houses built

Q2-Q3 2020

Rainwater and drinking water storage buffers constructed

Q2-Q3 2020

Luchtfoto 2020

jan 2020

Start demolition activities

Q3 2019

Start monitoring

JULY 2019

Houses/appartment building built and inhabed All CAWM equipment and infrastruvture installed and tested

JUNE 2019

Luchtfoto 2019

jan 2019

Start LIFE subsidy

JULY 2018

Situation before demolishing activities

APRIL 2018

Luchtfoto 2018

Luchtfoto 2018

jan 2018

Luchtfoto 2017

jan 2017

Four outdated appartment buildings are situated in the future Superlocal development area

MARCH 2015