Monitoring CAWM components in progress
FEB-MAY 2024
Re-Start monitoring effluent helophyte filter and digester
FEB-MAY 2024
Start monitoring rainwater treatment system
DEC 2023
Monitoring completed
JULY 2023
infiltration area incl wadi constructed
MAY 2023
rainwater gathering constructions completed (concrete pavement & gabions)
MAY 2023
Adjustments rainwater treatment plant/ testing phase completed
OCT 2022
inline monitoring testing phase completed
SEPT 2022
Digester constructed and tested
APRIL 2022
inline monitoring/ rainwater piping connected to storage buffer
MARCH 2022
First inhabitants apartment building
FEB 2022
Inline monitoring equipment flooded, construction infrastructure in progress
JAN 2022
Apartment building constructed
DEC 2021
Apartment building Indoor water saving installations/ food waste grinder installed
DEC 2021
Helophyte filter installed and tested
AUG 2021
rainwater treatment plant constructed & energy- and operating system installed
Q2-Q3 2021
Housing units rainwater treatment plant installed
MARCH 2021
15 Houses First inhabitants
JAN 2021
15 houses Indoor water saving installations/ food waste grinders installed
DEC 2020
15 Houses built
Q2-Q3 2020
Rainwater and drinking water storage buffers constructed
Q2-Q3 2020
Start demolition activities
Q3 2019
Start monitoring
JULY 2019
Houses/appartment building built and inhabed All CAWM equipment and infrastruvture installed and tested
JUNE 2019
Start LIFE subsidy
JULY 2018
Situation before demolishing activities
APRIL 2018
Four outdated appartment buildings are situated in the future Superlocal development area
MARCH 2015